Does Intervals have task dependencies? Meaning, if Task A is 5 hours, Task B has 2 hours, and Task C has 4 hours, will they all add up to 11 hours in this case and show next to the specific milestone that the tasks are associated with?
Intervals does not have task dependencies. The closest thing to task dependencies that it does have are milestones. We usually use milestones to group together several tasks into one deliverable. Then we schedule milestones along a timeline, knowing that each one needs to be completed before the next. This way we reschedule at the milestone level when timelines have to be moved, instead of moving around all of the tasks.